A power failure at Google Cloud’s London data center in late October caused a multi-hour outage that affected major UK financial and logistics services. The incident, which disrupted operations for companies including Lloyds Bank, HSBC, Royal Mail, and Revolut, was later attributed to a misconfiguration in the facility’s emergency power systems that prevented backup generators from activating as designed.
The outage occurred when an external underground power cable supplying the facility failed. At the time, the data center’s secondary utility feeder was offline for scheduled repairs, leaving the entire critical load dependent on a single power source. While the facility’s uninterruptible power supplies (UPS) initially provided temporary power, a flaw in the voltage-sensing logic and a misconfigured programmable logic controller (PLC) prevented the backup generators from receiving the automatic start signal. As a result, the UPS batteries depleted, leading to a complete loss of power to the affected availability zone.
What went wrong
Google’s europe-west-2-b facility in London uses a 2N utility power architecture, meaning it has fully redundant power paths for all critical systems. The site is designed to receive electricity from two independent utility feeders, labeled A and B, with a standby connection available for manual transfers during maintenance or emergencies. On the day of the outage, feeder B was intentionally taken offline to address issues identified during a quarterly generator load test conducted earlier in October. With feeder B out of service, feeder A became the sole source of utility power.
When the underground cable supplying feeder A failed, the facility’s UPS systems activated as expected, providing up to five minutes of runtime. However, the PLC responsible for managing the generator plant did not issue a start command because its logic incorrectly determined that a healthy utility source was still available. Google later confirmed that the PLC’s configuration did not account for a scenario in which both primary and secondary distribution feeds were de-energized simultaneously. Once the UPS batteries were exhausted, the data center lost power, triggering the outage.
- Outage occurred in Google Cloud’s europe-west-2-b London availability zone
- External underground power cable failure on feeder A triggered the incident
- Secondary feeder B was offline for repairs following a 14 October generator test
- UPS systems provided five minutes of runtime but generators failed to start
- PLC misconfiguration prevented automatic generator activation
Response and remediation
Google restored power to the facility by reconnecting to the utility grid and manually overriding the PLC. The company has since reprogrammed the controller to ensure it correctly identifies a total loss of utility power and issues the start command to generators. Additional changes to the electrical infrastructure at europe-west-2-b have been implemented and tested, including updates to voltage-sensing logic and expanded platform-wide testing for infrastructure-level events.
In its post-incident update, Google outlined two further action items. The first is a "communications enhancement" to develop an automated alert system for location-impacting incidents, aimed at improving notification speed to customers. The second involves expanding the scope of testing for infrastructure resilience to prevent similar failures in the future.
Impact and industry context
The outage highlighted the risks associated with single points of failure in redundant power architectures, even in top-tier cloud facilities. While Google’s 2N design is intended to eliminate such vulnerabilities, the incident demonstrated how misconfigurations or overlooked edge cases can undermine even the most robust systems. The disruption affected a range of high-profile UK services, including banking, postal, and fintech operations, underscoring the critical role of cloud infrastructure in modern digital economies.
For cloud operators, the event serves as a reminder of the importance of comprehensive testing for all possible failure modes, including rare or compound scenarios. The reliance on automated systems like PLCs introduces new layers of complexity, where even minor configuration errors can have cascading consequences. Google’s response—focusing on both technical fixes and improved communication—reflects a broader industry trend toward greater transparency and proactive incident management in cloud services.
Companies mentioned
Automated pipeline · Security
Synthesized from 1 industry feed on 5 Nov 2026. Passed independent editor verification (score 92/100) before publication. Style guide v1.4.
Sources
Decision trail
- Checking for duplicates — Deduped batch of 1 candidates
- Checking for duplicates — New story No recent article covers this specific Google London datacenter power outage incident.
- Writing the article — Draft created article_id=808 slug=google-cloud-london-outage-traced-to-generator-misconfiguration
-
Editor review — Approved
- Score: 92/100
- Factual grounding: The draft states the outage occurred 'in late October' but the source specifies the exact date as 20 October 2026. While 'late October' is technically correct, the precise date is available and should be used for clarity.
- Style compliance: The 'Key facts' block includes the date '14 October' for the generator test, but the draft does not explicitly state this date in the prose. While the fact is correct, it should be mentioned in the body for narrative flow.
- Style compliance: The standfirst mentions 'hours' for the outage duration, but the sources do not specify the exact duration. While 'multi-hour' is used later, the standfirst should avoid unsupported specifics.
- Generating reader Q&A — Generated 5 items
- Assigning hero image — Reused library image reused image #8
- Linking related stories — Linked 2 relations from 371 candidates
- Publishing — Published google-cloud-london-outage-traced-to-generator-misconfiguration
- Mastodon — Posted https://mstdn.social/@hostingpaper/117562748574622947




Discussion · coming soon
Be the first to join the thread when community discussion launches.